Size a continuous footing or grade beam, or a set of round post holes and sonotube columns. Get yards, bags and a ready-mix vs bags comparison.
Use this for a continuous footing or grade beam. For round post holes, switch to Post hole / column and enter diameter, depth and the number of holes.
Treats a solid poured stair as a triangular wedge. Treads equal risers minus one (the top landing is the upper floor). This is a planning volume, not a code check for rise and run.
- Volume
- –
- Cubic yards
- –
- 80 lb bags
- –
- 60 lb bags
- –
- Ready-mix material
- –
- Cost in 80 lb bags
- –
- Cost in 60 lb bags
- –
A 10% waste factor is a typical starting point. Use 10–15% on uneven subgrade, odd shapes, or pump jobs. Ready-mix planning prices along the Wasatch Front often land roughly $160–$210 per cubic yard before delivery or short-load fees — enter the quote you have. Bag counts use QUIKRETE Concrete Mix yields (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft) and round up to whole bags. Other brands may differ; check the bag.
Need footings or piers poured?
Request a quote from contractors serving Salt Lake, Davis, Weber and Utah counties.
Get a concrete quoteFootings vs. post holes
Use the footing tab for a rectangular trench: length in feet, width and depth in inches, times how many identical runs you have. Use the post hole / column tab for cylinders: diameter in inches, depth or height in feet, and a count. Stairs have their own stairs calculator. Everything also lives on the main concrete calculator.
Unit conversions you will actually use
One cubic yard equals 27 cubic feet. Thickness and footing width are usually measured in inches, so divide those by 12 before you multiply. A 20-by-24-foot driveway at 4 inches is 20 × 24 × (4 ÷ 12) = 160 cubic feet, which is 160 ÷ 27 ≈ 5.93 cubic yards before waste. With a 10% waste factor you would order about 6.52 yards — most people round the ticket up with their supplier.
An 80 lb bag of QUIKRETE Concrete Mix yields about 0.60 cubic feet, so a cubic yard is about 45 bags. A 60 lb bag yields about 0.45 cubic feet, or about 60 bags per yard. Other brands can differ; read the bag.
How much extra should you add for waste?
This calculator defaults to 10% extra, which is a reasonable starting point for a rectangular slab on a reasonably even, compacted base. Use 10–15% if the subgrade varies, the shape has curves or cutouts, or the concrete will be pumped. QUIKRETE’s own training example shows a slab that varies from 4 to 5 inches needing about 12.5% more than a flat 4-inch pour. It is cheaper to have a little left over than to short the pour and add a cold joint.
Ready-mix vs. 60 lb and 80 lb bags
Bags are practical for small jobs: a few post holes, a stoop repair, or a pad well under a cubic yard. Once you are around a yard or more, a ready-mix truck is usually easier, but plants often add a short-load fee when the order is under about 3–5 cubic yards. Enter your quoted price per yard, any short-load fee, and the bag prices you see at the store. The calculator will tell you which option is the lower material cost for this pour. Labor, forming, and delivery still sit on top of those numbers.
Wasatch Front ready-mix planning prices often land roughly $160–$210 per cubic yard before delivery or short-load fees. That is a planning range, not a quote — use the number on your ticket.
Related tools
City calculators:
Common questions
How do I calculate concrete for a footing?
For a continuous footing, multiply length in feet by width in inches ÷ 12 by depth in inches ÷ 12, then multiply by the number of identical footings and add waste. Divide by 27 for yards.
How do I calculate post-hole concrete?
Treat each hole as a cylinder: diameter in inches and depth in feet, times the number of holes. Use the Post hole / column tab on this page.
Bags or ready-mix for footings and post holes?
A handful of fence-post holes is usually a bag job. A long grade beam or a set of deck piers that adds up to a yard or more is often cheaper as ready-mix, unless a short-load fee is steep.
How deep should a post hole be in Utah?
Frost depth and your city’s requirements control this, not the calculator. Confirm depth with your contractor or building department, then enter the depth you will actually pour.