Concrete slab calculator
Enter length, width and thickness to get cubic yards, bag counts and a ready-mix vs bags comparison for a driveway, patio or pad.
Use this for a continuous footing or grade beam. For round post holes, switch to Post hole / column and enter diameter, depth and the number of holes.
Treats a solid poured stair as a triangular wedge. Treads equal risers minus one (the top landing is the upper floor). This is a planning volume, not a code check for rise and run.
- Volume
- –
- Cubic yards
- –
- 80 lb bags
- –
- 60 lb bags
- –
- Ready-mix material
- –
- Cost in 80 lb bags
- –
- Cost in 60 lb bags
- –
A 10% waste factor is a typical starting point. Use 10–15% on uneven subgrade, odd shapes, or pump jobs. Ready-mix planning prices along the Wasatch Front often land roughly $160–$210 per cubic yard before delivery or short-load fees — enter the quote you have. Bag counts use QUIKRETE Concrete Mix yields (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft) and round up to whole bags. Other brands may differ; check the bag.
Need the slab poured?
Request a quote from contractors who service Salt Lake, Davis, Weber and Utah counties.
Get a concrete quoteWhat this slab calculator is for
This page is locked to a rectangular slab so you can focus on area and thickness. Switch to the main concrete calculator for footings, post holes or stairs, or open the driveway and patio cost pages if you also want an installed planning range.
Unit conversions you will actually use
One cubic yard equals 27 cubic feet. Thickness and footing width are usually measured in inches, so divide those by 12 before you multiply. A 20-by-24-foot driveway at 4 inches is 20 × 24 × (4 ÷ 12) = 160 cubic feet, which is 160 ÷ 27 ≈ 5.93 cubic yards before waste. With a 10% waste factor you would order about 6.52 yards — most people round the ticket up with their supplier.
An 80 lb bag of QUIKRETE Concrete Mix yields about 0.60 cubic feet, so a cubic yard is about 45 bags. A 60 lb bag yields about 0.45 cubic feet, or about 60 bags per yard. Other brands can differ; read the bag.
How much extra should you add for waste?
This calculator defaults to 10% extra, which is a reasonable starting point for a rectangular slab on a reasonably even, compacted base. Use 10–15% if the subgrade varies, the shape has curves or cutouts, or the concrete will be pumped. QUIKRETE’s own training example shows a slab that varies from 4 to 5 inches needing about 12.5% more than a flat 4-inch pour. It is cheaper to have a little left over than to short the pour and add a cold joint.
Ready-mix vs. 60 lb and 80 lb bags
Bags are practical for small jobs: a few post holes, a stoop repair, or a pad well under a cubic yard. Once you are around a yard or more, a ready-mix truck is usually easier, but plants often add a short-load fee when the order is under about 3–5 cubic yards. Enter your quoted price per yard, any short-load fee, and the bag prices you see at the store. The calculator will tell you which option is the lower material cost for this pour. Labor, forming, and delivery still sit on top of those numbers.
Wasatch Front ready-mix planning prices often land roughly $160–$210 per cubic yard before delivery or short-load fees. That is a planning range, not a quote — use the number on your ticket.
Related tools
City calculators:
Common questions
How do I use a concrete slab calculator?
Enter length and width in feet and thickness in inches. The tool converts to cubic feet and cubic yards, adds waste, and shows 60 lb and 80 lb bag counts.
How thick should a driveway or patio slab be?
Four inches is common for patios, walks and passenger-car driveways. Five to six inches is often used where trucks or RVs will park. Follow your city and your contractor.
How many yards for a 16×20 patio at 4 inches?
16 × 20 × 4 ÷ 12 ÷ 27 ≈ 3.95 yards before waste, or about 4.35 yards with 10% extra.
Bags or a truck for a slab?
A typical patio or driveway is several yards, so ready-mix is usually the practical choice. Compare costs on this page if you also have a short-load fee.