Concrete wall calculator
Cubic yards and bag counts for a poured foundation, stem or retaining wall. Add the footing, total the project and send the numbers to a local pro.
- Free, no sign-up
- Bag math from QUIKRETE data sheets
- Wasatch Front prices you can edit
- Share, print or total several pours
For a round patio, fire-pit pad or hot-tub pad. Measure straight across the widest point.
For a poured foundation, stem or retaining wall. Figure the footing on the Footing tab, then use Add to my project to total both.
Use this for a continuous footing or grade beam. For round post holes, switch to Post hole / column. Wasatch Front building departments commonly set frost depth at 30 inches; see frost line depth in Utah.
Treats a solid poured stair as a triangular wedge. Treads equal risers minus one (the top landing is the upper floor). This is a planning volume, not a code check for rise and run.
Curb depth is the curb's thickness front to back; curb height runs from its bottom to its top. Work in the public right-of-way usually needs a city permit and the city's standard dimensions.
Waste & prices
–cubic yards to order, waste included
– · – · –
- Ready-mix material + short-load fee
- –
- Cost in 80 lb bags
- –
- Cost in 60 lb bags
- –
- Ready-mix truck loads
- –
Rebar, gravel base & forms for this slab
- Rebar grid
- –
- Gravel base
- –
- Form boards (perimeter)
- –
Rebar assumes a grid both ways, 3 inches in from each edge, plus 10% for laps and offcuts. Gravel tons use about 1.4 tons per cubic yard; it varies by material, so ask your supplier. Planning numbers only: your contractor or plans set bar size and spacing.
My project
Project total: –
A 10% waste factor is a typical starting point. Use 10–15% on uneven subgrade, odd shapes, or pump jobs. Ready-mix planning prices along the Wasatch Front often land roughly $160–$210 per cubic yard before delivery or short-load fees — enter the quote you have. Bag counts use QUIKRETE Concrete Mix yields (80 lb ≈ 0.60, 60 lb ≈ 0.45, 50 lb ≈ 0.375, 40 lb ≈ 0.30 cu ft) and round up to whole bags. Weight uses about 145 lb per cubic foot. Other brands may differ; check the bag.
Need a wall formed and poured?
Share the job with up to 3 contractors who service Salt Lake, Davis, Weber and Utah counties.
Get a concrete quoteHow the wall math works
A straight wall is a box: length × height × thickness. Convert the thickness from inches to feet first (8 in ÷ 12 = 0.667 ft). A 30-foot wall, 4 feet tall and 8 inches thick, is 30 × 4 × 0.667 = 80 cubic feet, or 80 ÷ 27 = 2.96 cubic yards. With 10% waste, order about 3.26 yards. For an L-shaped or stepped wall, enter each straight run separately and use Add to my project.
Footings sit under the wall and below the frost line. Along the Wasatch Front building departments commonly publish a 30-inch frost depth; see frost line depth in Utah. Retaining walls above a few feet, or walls holding up a driveway or a slope, usually need an engineer and a permit.
Unit conversions you will actually use
One cubic yard equals 27 cubic feet. Thickness and footing width are usually measured in inches, so divide those by 12 before you multiply. A 20-by-24-foot driveway at 4 inches is 20 × 24 × (4 ÷ 12) = 160 cubic feet, which is 160 ÷ 27 ≈ 5.93 cubic yards before waste. With a 10% waste factor you would order about 6.52 yards — most people round the ticket up with their supplier.
An 80 lb bag of QUIKRETE Concrete Mix yields about 0.60 cubic feet, so a cubic yard is about 45 bags. A 60 lb bag yields about 0.45 cubic feet, or about 60 bags per yard. Other brands can differ; read the bag.
How much extra should you add for waste?
This calculator defaults to 10% extra, which is a reasonable starting point for a rectangular slab on a reasonably even, compacted base. Use 10–15% if the subgrade varies, the shape has curves or cutouts, or the concrete will be pumped. QUIKRETE’s own training example shows a slab that varies from 4 to 5 inches needing about 12.5% more than a flat 4-inch pour. It is cheaper to have a little left over than to short the pour and add a cold joint.
Ready-mix vs. 60 lb and 80 lb bags
Bags are practical for small jobs: a few post holes, a stoop repair, or a pad well under a cubic yard. Once you are around a yard or more, a ready-mix truck is usually easier, but plants often add a short-load fee when the order is under about 3–5 cubic yards. Enter your quoted price per yard, any short-load fee, and the bag prices you see at the store. The calculator will tell you which option is the lower material cost for this pour. Labor, forming, and delivery still sit on top of those numbers.
Wasatch Front ready-mix planning prices often land roughly $160–$210 per cubic yard before delivery or short-load fees. That is a planning range, not a quote — use the number on your ticket.
Related concrete calculators
Common questions
How do I calculate concrete for a wall?
Multiply length (ft) × height (ft) × thickness (in ÷ 12) to get cubic feet, divide by 27 for cubic yards, then add 5–10% waste. A 30 ft × 4 ft wall 8 in thick is 80 cubic feet, about 2.96 yards before waste.
Does this include the footing?
No. Figure the footing on the Footing tab, press Add to my project for each part, and the project total adds them.
How thick should a poured foundation or retaining wall be?
That is an engineering and code question, not a calculator one. Many residential foundation walls are 8 inches thick, but height, soil and loads change that. Retaining walls over a few feet usually need an engineered design and a permit; ask your city.
Bags or ready-mix for a wall?
Walls add up fast. Even a short 8-inch wall can pass a cubic yard, which is 45 bags of 80 lb mix. Most walls go to a ready-mix truck, often with a pump.